20+ Celebrating 20+ Years of Solar ExcellenceSince 200520 GW shipped to 120+ countries Our story→
Home/News/Industry News
Industry News · 2026-11-23

California State University Bakersfield details a 4.55 MWdc solar and 11.7 MWh storage plan

A California environmental notice describes a 4.55 MWdc campus solar project with 11.7 MWh of storage across 15 acres, plus a 21 kV grid connection.

California State University Bakersfield details a 4.55 MWdc solar and 11.7 MWh storage plan

A California environmental notice for California State University, Bakersfield describes a proposed campus project combining 4.55 MWdc of solar generation with an 11.7 MWh battery energy storage system. The listed site covers 15 acres and includes approximately 6,500 panels mounted on about 1,275 posts.

The notice also specifies an underground grid connection rated at 21 kV, extending about 825 feet. These figures define the documented project scope; the notice is not a vendor award or an invitation to bid, and it does not establish that construction has been completed.

For EPCs and equipment suppliers, the case provides a useful scale reference for campus solar-plus-storage design. Early procurement review should connect array layout, structural quantities, battery siting, protection, medium-voltage equipment and interconnection scope, while confirming the latest permitting documents and issued procurement packages before making commercial assumptions.

Source date: 2026-11-20. Source: California Environmental Quality Act database. Slug: csu-bakersfield-4-55mw-11-7mwh-solar-storage.